Werribee Street Level Crossing

As part of the Victorian Government Level Crossing Removal Project, a new rail bridge will be built over Werribee Street to remove the Werribee level crossing.

Wamarra has completed the site establishment carpentry works on behalf of McConnell Dowell as part of the Werribee Street Level Crossing Removal for Western Program Alliance (WPA).

Project features included the design of the temporary structure, covered walkways (740m2), a covered pre-start area (290m2), concrete paving (225m2), timber decking (675m2), access stairs and ramps and handrails.

Wamarra provided design, management, trades, and all materials to successfully complete the construction of the compound safely and on schedule.

Following the completion of the contract scope, Wamarra was engaged to perform additional works.

Project Summary

sectorRoads and Bridges
locationWerribee, VIC
clientMcConnell Dowell (WPA)

Expression of Interest

We’re always on the lookout for ambitious, career-minded people to join our team. Submit your details below and introduce yourself! We’ll keep you informed about any upcoming job opportunities at Wamarra.
    • DD slash MM slash YYYY
    • Accepted file types: doc, docx, Max. file size: 2 MB.
      accepted file formats are .doc and .docx
    • Accepted file types: doc, docx, Max. file size: 2 MB.
      accepted file formats are .doc and .docx